NESCOT College
Areas of NESCOT's North Wing and various other parts of the college rewired in 10 weeks, with zero defects at handover and further contracts awarded since.
Epsom, 10 weeks

Internal and external lighting at Nell Gwynn School rewired with LED fittings, emergency lighting and occupancy controls, room by room while the nursery stayed open.
We completed a full rewire of the internal and external lighting at Nell Gwynn School, installing energy-efficient LED fittings throughout, alongside new emergency lighting and occupancy sensors and PIR controls to reduce unnecessary energy use.
With the nursery remaining open throughout the works, careful planning was essential. We agreed a room-by-room programme with the nursery team, coordinating access and completing each area in sequence to keep disruption to staff and children to a minimum.
Working to a fixed timescale, we completed, tested and certified the installation on time and within budget, providing improved lighting and greater control over running costs.
From installation to certification.
The nursery stayed open throughout, so the work was planned room by room with the nursery team.
| The challenge | How we handled it |
|---|---|
| A nursery still open | How we handled it: A room-by-room programme agreed with the nursery team, with access coordinated and each area finished in sequence |
| A fixed timescale | How we handled it: Completed, tested and certified on time and within budget |





Areas of NESCOT's North Wing and various other parts of the college rewired in 10 weeks, with zero defects at handover and further contracts awarded since.
Epsom, 10 weeks

An EICR and everything it called for, from a new board to emergency and LED lighting, done in two weeks around a clubhouse still in use, for EAP Devlin & Sons.
Wimbledon, 2 weeks
Send the drawings and programme, and we'll come back with questions or a price.